Phase 7B and 9A Construction in Full Swing

Crossings Development Update

As part of the Crossings Phases 7B and 9A developments, construction will be occurring in the areas highlighted on the attached figure. Grading has already begun behind the existing Crossing phases, adjacent to Metis Trail West, as well as to the west of Caledonia Park between Caledonia Boulevard West and Halifax Road West. Construction activities for this portion of development include topsoil stripping to stockpile and earthmoving with an estimate completion in mid to end of May 2025.

Deep utility construction has already started in Phase 7B on Caledonia Boulevard West, which will be followed by installations on Halifax Road West. Surface construction in this area is expected to be finished in June 2025. Construction includes extensions to water, sewer, and storm lines, followed by sidewalk and road construction.

During this time, you will also notice that the City of Lethbridge Electric Utility will be working to bury a portion of their overhead line between Halifax Road and Caledonia Boulevard West. As well construction of the new Holy Spirit school will also begin work on their site that is south of the existing Caledonia Park.

Crossings Phase 9A deep utilities will begin end of April or early May and continue through June. Surface construction will follow from June into late August 2025. Construction will include water, sewer, and storm line installations, followed by sidewalk and road construction.

Shallow utility residential installations will follow soon after surface is complete at the end of August.

As summer approaches you should start to see the Phase 9A Park start to take shape, we expect that construction to start in July and continue up until October/November of this year. Construction will include fine grading in the storm pond, along with loaming/seeding, planting of trees, shrubs and aquatic materials, pathway installation, and playground equipment installation.

All construction will be conducted in accordance with the current City of Lethbridge Noise Bylaw #5270. Dust control will be performed as needed by the contractor undertaking the work. The attached figure details the approximate timing of construction in Phases 7B & 9A.

For inquiries, please contact 311 or:

City of Lethbridge
Lethbridge Land
(403) 359-6547

 
 

Stantec Consulting Ltd.
Community Development
(403) 329-3344